Data / Environmental compliance / Missouri / New Madrid Power Plant

New Madrid Power Plant, Marston, MO: $16,800 in penalties

Updated November 7, 2026. Source: US EPA, Enforcement and Compliance History Online (ECHO).

EPA's ECHO database records 7 inspections, 3 informal enforcement actions and 2 formal enforcement actions at New Madrid Power Plant, 41 St. Jude Road, Marston, MO 63866, in the five years to November 1, 2026. Penalties total $16,800, the latest $10,500 on March 21, 2022. The facility had violations in 3 of the last 12 quarters.

The request: Get every facility in Electric Power Generation, Transmission and Distribution in Missouri with penalties and violations. $10 of work on sign-up, no card.

SpecStream is the live web data engine for teams and agents. It reads EPA's enforcement and compliance records, and this page is that reading. Ask for the facilities you check by industry, state or program and new inspections, violations and penalties arrive in your sheet, CRM, Slack or agent as EPA and the states record them.

Site
41 St. Jude Road, Marston, MO 63866
EPA registry ID (FRS)
110000606336
Industry
22111 Electric Power Generation; 221112 Fossil Fuel Electric Power Generation; 221122 Electric Power Distribution; 49111 Postal Service
County
New Madrid
Programs
Clean Air Act, Clean Water Act, Hazardous waste (RCRA)
Compliance status
Violation Identified
Inspections
7, latest August 20, 2026
Formal actions
2, latest April 8, 2025
Informal actions
3, latest December 8, 2022
Penalties
$16,800 in 2 penalties
ECHO facility report
echo.epa.gov

By program

Inspections, enforcement actions and penalties of the last five years in each EPA program that covers the facility, as the program systems record them. Federal case penalties are listed under federal enforcement cases. Quarters count the last 12.

ProgramInspectionsInformal actionsFormal actionsPenaltiesLatest penaltyLatest amountQuarters with violationsQuarters in significant noncomplianceStatus
Clean Air Act521$10,500March 21, 2022$10,50000No Violation Identified
Clean Water Act110$0$040Violation Identified
Hazardous waste (RCRA)000$0$000No Violation Identified

Federal enforcement cases

EPA cases that name this facility, newest first. The penalty is the whole case penalty, shared with the other facilities named in the case.

CaseCase nameStatus dateTypeStatusOutcomeStatutesCase penaltyFacilities in caseSource
07-2025-0039Associated Electric Cooperative, Inc. CAA 113D1 Action For Penalty, 112(r) RMP ExpeditedMay 8, 2025Administrative, FormalClosedFinal Order With PenaltyClean Air Act$6,3002echo.epa.gov

EPA inspections and evaluations

Compliance monitoring EPA itself carried out, newest first. State inspections are counted above, with the date of the latest.

DateActivityTypeLaw
May 14, 2024Inspection/Evaluation112(r)(7) InspectionClean Air Act
May 14, 2024Inspection/Evaluation112(r)(7) InspectionClean Air Act
May 14, 2024Inspection/EvaluationEvaluationEPCRA

Also on SpecStream

Public domain (U.S. government work). Counts and penalties cover the five years to November 1, 2026 as ECHO publishes them in its exporter and case downloads, drawn from EPA's air, water, hazardous waste and drinking water systems and from the states that report to them. Records can be incomplete, late or corrected after this page was read. A federal case penalty that names several facilities is shown on each of them and counted once in industry, state and national totals. Each row links to EPA's own report. A quarter in significant noncompliance is EPA's term for a serious violation status in a program, not a finding of fault beyond that status. This page uses US EPA data and is not endorsed or certified by the US EPA. Free to reuse with credit to SpecStream under CC BY 4.0. Spot a wrong value? Write to [email protected] with the link to this page.