Witman Plumbing Inc., Palatine, IL: 8 OSHA citations, $31,466 in penalties (2025)
OSHA recorded 1 inspection at Witman Plumbing Inc., 1329 Rand Road, Palatine, IL 60074, on July 31, 2025. 1 inspection ended in citations: 8 citations with $31,466 in initial penalties and $31,466 in current penalties. The latest citation was issued December 22, 2025.
SpecStream is the live web data engine for teams and agents. It reads OSHA inspections and citations from the US Department of Labor's enforcement data, and this page is that reading. Ask for the employers you check by industry, state or standard and new inspections and citations arrive in your sheet, CRM, Slack or agent as they are posted.
- Site
- 1329 Rand Road, Palatine, IL 60074
- Industry
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Ownership
- Private
- Employees at the site
- 6 (as recorded at the latest inspection)
- Inspections
- 1, of which 1 with citations
- Citations
- 8
- Penalties
- $31,466 initial, $31,466 current
Inspections
Every inspection OSHA opened at this site since November 3, 2021.
| Opened | Closed | Type | Scope | Focus | Citations | Current penalties | Source |
|---|---|---|---|---|---|---|---|
| July 31, 2025 | September 1, 2026 | Planned | Partial | Safety | 8 | $31,466 | osha.gov |
Citations
One row for each citation, newest first. Gravity is OSHA's level of gravity for serious violations.
| Inspection opened | Standard cited | Standard title | Type | Gravity | Issued | Initial penalty | Current penalty | Source |
|---|---|---|---|---|---|---|---|---|
| July 31, 2025 | 1903.19(c)(1) | Abatement verification | Other than serious | Not listed | December 22, 2025 | $398 | $398 | osha.gov |
| July 31, 2025 | 1926.652(a)(1) | Requirements for protective systems | Repeat | 10 | September 24, 2025 | $9,930 | $9,930 | osha.gov |
| July 31, 2025 | 1926.100(a) | Head protection | Repeat | 5 | September 24, 2025 | $5,674 | $5,674 | osha.gov |
| July 31, 2025 | 1926.1053(b)(16) | Ladders | Serious | 1 | September 24, 2025 | $2,128 | $2,128 | osha.gov |
| July 31, 2025 | 1926.1053(b)(1) | Ladders | Serious | 5 | September 24, 2025 | $2,837 | $2,837 | osha.gov |
| July 31, 2025 | 1926.651(i)(3) | Specific excavation requirements | Serious | 5 | September 24, 2025 | $3,547 | $3,547 | osha.gov |
| July 31, 2025 | 1926.651(e) | Specific excavation requirements | Serious | 5 | September 24, 2025 | $3,405 | $3,405 | osha.gov |
| July 31, 2025 | 1926.416(e)(1) | General requirements | Serious | 5 | September 24, 2025 | $3,547 | $3,547 | osha.gov |
Also on SpecStream
- All OSHA citations in Building Equipment Contractors in Illinois
- OSHA citations in Illinois
- 29 CFR 1926.651, Specific excavation requirements: all citations
- 29 CFR 1926.1053, Ladders: all citations
- 29 CFR 1926.416, General requirements: all citations
Updated November 3, 2026. Read from US Department of Labor, OSHA enforcement data. Public domain (U.S. government work). Penalties are as OSHA records them on the date this page was read and can change after a contest or a settlement. Citations OSHA deleted are left out. Each row links to OSHA's own inspection record. This page uses US Department of Labor data and is not endorsed or certified by the US Department of Labor. Free to reuse with credit to SpecStream under CC BY 4.0. Spot a wrong value? Write to [email protected] with the link to this page.