OSHA recorded 3 inspections at Products Unlimited, Inc., 915 North 43RD Ave., Omaha, NE 68131, between February 15, 2022 and December 18, 2025. 3 inspections ended in citations: 35 citations with $345,561 in initial penalties and $325,768 in current penalties. The latest citation was issued June 2, 2026.
SpecStream is the live web data engine for teams and agents. It reads OSHA inspections and citations from the US Department of Labor's enforcement data, and this page is that reading. Ask for the employers you check by industry, state or standard and new inspections and citations arrive in your sheet, CRM, Slack or agent as they are posted.
- Site
- 915 North 43RD Ave., Omaha, NE 68131
- Industry
- 313230 Nonwoven Fabric Mills
- Ownership
- Private
- Employees at the site
- 63 (as recorded at the latest inspection)
- Inspections
- 3, of which 3 with citations
- Citations
- 35
- Penalties
- $345,561 initial, $325,768 current
Inspections
Every inspection OSHA opened at this site since November 3, 2021.
| Opened | Closed | Type | Scope | Focus | Citations | Current penalties | Source |
|---|---|---|---|---|---|---|---|
| December 18, 2025 | Referral | Partial | Safety | 25 | $293,372 | osha.gov | |
| March 9, 2022 | September 6, 2024 | Referral | Partial | Health | 5 | $14,996 | osha.gov |
| February 15, 2022 | June 12, 2024 | Referral | Partial | Safety | 5 | $17,400 | osha.gov |
Citations
One row for each citation, newest first. Gravity is OSHA's level of gravity for serious violations.
| Inspection opened | Standard cited | Standard title | Type | Gravity | Issued | Initial penalty | Current penalty | Source |
|---|---|---|---|---|---|---|---|---|
| December 18, 2025 | 1910.305(g)(1)(iv) | Wiring methods, components, and equipment for general use | Other than serious | Not listed | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.305(a)(2)(i) | Wiring methods, components, and equipment for general use | Other than serious | Not listed | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.212(a)(1) | General requirements for all machines | Repeat | 10 | June 2, 2026 | $35,748 | $35,748 | osha.gov |
| December 18, 2025 | 1910.147(d) | The control of hazardous energy (lockout/tagout) | Repeat | 10 | June 2, 2026 | $35,748 | $35,748 | osha.gov |
| December 18, 2025 | 1910.147(c)(7)(i) | The control of hazardous energy (lockout/tagout) | Repeat | 10 | June 2, 2026 | $35,748 | $35,748 | osha.gov |
| December 18, 2025 | 1910.335(a)(2)(ii) | Safeguards for personnel protection | Serious | 10 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.335(a)(2)(i) | Safeguards for personnel protection | Serious | 10 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.335(a)(1)(i) | Safeguards for personnel protection | Serious | 10 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.332(b)(1) | Training | Serious | 10 | June 2, 2026 | $16,550 | $16,550 | osha.gov |
| December 18, 2025 | 1910.305(b)(1)(i) | Wiring methods, components, and equipment for general use | Serious | 10 | June 2, 2026 | $16,550 | $16,550 | osha.gov |
| December 18, 2025 | 1910.303(g)(2)(i) | General | Serious | 10 | June 2, 2026 | $16,550 | $16,550 | osha.gov |
| December 18, 2025 | 1910.219(f)(3) | Mechanical power-transmission apparatus | Serious | 10 | June 2, 2026 | $16,550 | $16,550 | osha.gov |
| December 18, 2025 | 1910.178(l)(6) | Powered industrial trucks | Serious | 5 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.178(l)(1)(i) | Powered industrial trucks | Serious | 5 | June 2, 2026 | $10,214 | $10,214 | osha.gov |
| December 18, 2025 | 1910.147(f)(3)(ii) | The control of hazardous energy (lockout/tagout) | Serious | 10 | June 2, 2026 | $16,550 | $16,550 | osha.gov |
| December 18, 2025 | 1910.147(c)(6)(ii) | The control of hazardous energy (lockout/tagout) | Serious | 10 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.147(c)(4)(ii) | The control of hazardous energy (lockout/tagout) | Serious | 10 | June 2, 2026 | $16,550 | $16,550 | osha.gov |
| December 18, 2025 | 1910.146(k)(3) | Permit-required confined spaces | Serious | 5 | June 2, 2026 | $12,769 | $12,769 | osha.gov |
| December 18, 2025 | 1910.146(g)(4) | Permit-required confined spaces | Serious | 5 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.146(g)(1) | Permit-required confined spaces | Serious | 5 | June 2, 2026 | $12,769 | $12,769 | osha.gov |
| December 18, 2025 | 1910.146(d)(5) | Permit-required confined spaces | Serious | 5 | June 2, 2026 | $12,769 | $12,769 | osha.gov |
| December 18, 2025 | 1910.146(e)(1) | Permit-required confined spaces | Serious | 5 | June 2, 2026 | $0 | $0 | osha.gov |
| December 18, 2025 | 1910.146(d)(3)(iii) | Permit-required confined spaces | Serious | 5 | June 2, 2026 | $12,769 | $12,769 | osha.gov |
| December 18, 2025 | 1910.30(a)(1) | Training requirements | Serious | 5 | June 2, 2026 | $12,769 | $12,769 | osha.gov |
| December 18, 2025 | 1910.28(b)(1)(i) | Duty to have fall protection and falling object protection | Serious | 5 | June 2, 2026 | $12,769 | $12,769 | osha.gov |
| March 9, 2022 | 1903.19(c)(1) | Abatement verification | Other than serious | Not listed | July 10, 2024 | $996 | $996 | osha.gov |
| March 9, 2022 | 1910.134(c)(2)(i) | Respiratory protection | Other than serious | Not listed | August 24, 2022 | $0 | $0 | osha.gov |
| March 9, 2022 | 1910.307(c) | Hazardous (classified) locations | Serious | 10 | August 24, 2022 | $0 | $0 | osha.gov |
| March 9, 2022 | 1910.307(b) | Hazardous (classified) locations | Serious | 10 | August 24, 2022 | $11,167 | $7,000 | osha.gov |
| March 9, 2022 | 1910.22(a)(1) | General requirements | Serious | 10 | August 24, 2022 | $11,167 | $7,000 | osha.gov |
| February 15, 2022 | 1910.252(b)(2)(iii) | General requirements | Serious | 1 | May 13, 2022 | $0 | $0 | osha.gov |
| February 15, 2022 | 1910.252(b)(2)(i) | General requirements | Serious | 1 | May 13, 2022 | $0 | $0 | osha.gov |
| February 15, 2022 | 1910.252(a)(2)(xiii) | General requirements | Serious | 1 | May 13, 2022 | $6,153 | $3,900 | osha.gov |
| February 15, 2022 | 1910.212(a)(1) | General requirements for all machines | Serious | 10 | May 13, 2022 | $14,502 | $8,700 | osha.gov |
| February 15, 2022 | 1910.28(b)(3)(ii) | Duty to have fall protection and falling object protection | Serious | 5 | May 13, 2022 | $8,204 | $4,800 | osha.gov |
Also on SpecStream
- OSHA citations in Nebraska
- 29 CFR 1910.146, Permit-required confined spaces: all citations
- 29 CFR 1910.147, The control of hazardous energy (lockout/tagout): all citations
- 29 CFR 1910.305, Wiring methods, components, and equipment for general use: all citations
Updated November 3, 2026. Read from US Department of Labor, OSHA enforcement data. Public domain (U.S. government work). Penalties are as OSHA records them on the date this page was read and can change after a contest or a settlement. Citations OSHA deleted are left out. Each row links to OSHA's own inspection record. This page uses US Department of Labor data and is not endorsed or certified by the US Department of Labor. Free to reuse with credit to SpecStream under CC BY 4.0. Spot a wrong value? Write to [email protected] with the link to this page.