Improvements to Generator Interconnection Procedures and Agreements
The Federal Energy Regulatory Commission published this final rule in the Federal Register on April 16, 2024. It took effect on May 16, 2024.
SpecStream is the live web data engine for teams and agents. It reads every rule and proposed rule in the Federal Register each morning, and this page is that reading. Name your industry once and new rules, comment deadlines and effective dates arrive in your sheet, CRM, Slack or agent as they are published.
What the agency says
In this order, the Federal Energy Regulatory Commission addresses arguments raised on rehearing, sets aside, in part, and clarifies Order No. 2023, which amended the Commission's regulations and its pro forma Large Generator Interconnection Procedures, pro forma Large Generator Interconnection Agreement, pro forma Small Generator Interconnection Procedures, and pro forma Small Generator Interconnection Agreement to address interconnection queue backlogs, improve certainty, and prevent undue discrimination for new technologies.
Key facts
- Document number
- 2024-06563
- Type
- Final rule
- Action
- Order on rehearing and clarification
- Agency
- Energy Department; Federal Energy Regulatory Commission
- Published
- April 16, 2024
- Takes effect
- May 16, 2024
- Dates
- This rule is effective May 16, 2024.
- Docket
- Docket No. RM22-14-001; Order No. 2023-A
- Code of Federal Regulations
- 18 CFR 35
- Pages
- 238
Other documents from the Federal Energy Regulatory Commission
| Document | Type | Published |
|---|---|---|
| Authorizations for Certain Activities at Liquefied Natural Gas Plants 2026-21443 | Proposed rule | Oct 20 |
| Categorical Exclusion Under the National Environmental Policy Act for Certain Terminations or Revocations of Water Power Licenses or Exemptions 2026-14878 | Final rule | Jul 23 |
| Revisions to Financial Forms Reporting and Filing Requirements; Correction 2026-13726 | Proposed rule | Jul 7 |
| Revisions to Financial Forms Reporting and Filing Requirements 2026-12712 | Proposed rule | Jun 24 |
| Standards for Business Practices of Interstate Natural Gas Pipelines 2026-10600 | Final rule | May 28 |
| Revisions to the Blanket Certificate Program 2026-10498 | Proposed rule | May 27 |
| Five-Year Review of the Oil Pipeline Index 2026-08264 | Final rule | Apr 28 |
| Annual Update to Fee Schedule for the Use of Government Lands by Hydropower Licensees 2026-07773 | Final rule | Apr 21 |
Everything from the Federal Energy Regulatory Commission · Published in April 2024