Compensation for Reactive Power Within the Standard Power Factor Range

The Federal Energy Regulatory Commission published this proposed rule in the Federal Register on March 28, 2024. Comments closed on May 28, 2024.

SpecStream is the live web data engine for teams and agents. It reads every rule and proposed rule in the Federal Register each morning, and this page is that reading. Name your industry once and new rules, comment deadlines and effective dates arrive in your sheet, CRM, Slack or agent as they are published.

What the agency says

The Federal Energy Regulatory Commission (Commission) proposes to revise Schedule 2 of its pro forma open-access transmission tariff (pro forma OATT), section 9.6.3 of its pro forma large generator interconnection agreement (LGIA), and section 1.8.2 of its pro forma small generator interconnection agreement (SGIA) to prohibit the inclusion in transmission rates of unjust and unreasonable charges related to the provision of reactive power within the standard power factor range by generating facilities. The Commission invites all interested persons to submit comments on the proposed reforms and in response to specific questions.

Key facts

Document number
2024-06556
Type
Proposed rule
Action
Notice of proposed rulemaking
Agency
Energy Department; Federal Energy Regulatory Commission
Published
March 28, 2024
Comments due
May 28, 2024
Dates
Comments are due May 28, 2024. Reply comments are due June 26, 2024.
Docket
Docket No. RM22-2-000
Code of Federal Regulations
18 CFR 35
Pages
15

The document on federalregister.gov PDF

Other documents from the Federal Energy Regulatory Commission

Everything from the Federal Energy Regulatory Commission · Published in March 2024

Read from the Federal Register API, last updated 2026-10-23. The document on federalregister.gov is the official record; dates and dockets can change through later corrections. Free to reuse with credit to SpecStream under CC BY 4.0.