The Federal Energy Regulatory Commission published this final rule in the Federal Register on June 11, 2024. It took effect on August 12, 2024.

SpecStream is the live web data engine for teams and agents. It reads every rule and proposed rule in the Federal Register each morning, and this page is that reading. Name your industry once and new rules, comment deadlines and effective dates arrive in your sheet, CRM, Slack or agent as they are published.

What the agency says

The Federal Energy Regulatory Commission (Commission) revises the pro forma Open Access Transmission Tariff (OATT) to remedy deficiencies in the Commission's existing regional and local transmission planning and cost allocation requirements. In this final order, the Commission requires transmission providers to conduct Long- Term Regional Transmission Planning that will ensure the identification, evaluation, and selection, as well as the allocation of the costs, of more efficient or cost-effective regional transmission solutions to address Long-Term Transmission Needs. The Commission also directs other reforms to improve coordination of regional transmission planning and generator interconnection processes, require consideration of certain alternative transmission technologies in regional transmission planning processes, and improve transparency of local transmission planning processes and coordination between regional and local transmission planning processes. These reforms are intended to ensure that existing regional and local transmission planning and cost allocation requirements are just, reasonable, and not unduly discriminatory or preferential.

Key facts

Document number
2024-10872
Type
Final rule
Action
Final order
Agency
Energy Department; Federal Energy Regulatory Commission
Published
June 11, 2024
Takes effect
August 12, 2024
Dates
This final order is effective August 12, 2024.
Docket
Docket No. RM21-17-000; Order No. 1920
Code of Federal Regulations
18 CFR 35
Topics
Electric power rates; Electric utilities; Reporting and recordkeeping requirements
Pages
307

The document on federalregister.gov PDF

Other documents from the Federal Energy Regulatory Commission

Everything from the Federal Energy Regulatory Commission · Rules on electric power rates · Rules on electric utilities · Rules on reporting and recordkeeping requirements · Published in June 2024

Read from the Federal Register API, last updated 2026-10-24. The document on federalregister.gov is the official record; dates and dockets can change through later corrections. Free to reuse with credit to SpecStream under CC BY 4.0.