DHM DESIGN CORPORATION: 97 federal contract awards, $17.9 million obligated (FY2024 to FY2027)
DHM DESIGN CORPORATION (UEI JSAFS55GW4B6), Denver, CO, received 97 federal prime contract awards with $17.9 million obligated in fiscal years 2024 to 2027, from 2 agencies under 4 NAICS codes. Its largest buyer is Department of the Interior ($17.7 million) and its largest code is NAICS 541310 Architectural Services.
SpecStream is the live web data engine for teams and agents. It reads every federal contract award on USAspending.gov and every open opportunity on SAM.gov, and this page is that reading. Ask for the awards in your niche and the winners, agencies, values and recompetes arrive in your sheet, CRM, Slack or agent as they are reported.
- JSAFS55GW4B6UEI
- Denver, COLocation
- Small BusinessBusiness size
- 97Contract awards
- $17.9 millionObligated
- 2023-10-24First action in window
- 2026-09-26Latest action
Where the work is
NAICS codes, with the other winners in each.
| NAICS | Industry | Awards | Obligated |
|---|---|---|---|
| 541310 | Architectural Services | 45 | $12.9 million |
| 541330 | Engineering Services | 50 | $4.9 million |
| 541320 | Landscape Architectural Services | 1 | $66,808 |
| 115310 | Support Activities for Forestry | 1 | $0 |
Buying agencies
| Agency | Awards | Obligated |
|---|---|---|
| Department of the Interior | 94 | $17.7 million |
| Department of Agriculture | 3 | $158,261 |
Obligations by fiscal year
| Fiscal year | Obligated |
|---|---|
| FY2024 | $5.5 million |
| FY2025 | $4.6 million |
| FY2026 | $7.8 million |
Contract awards
The 50 largest of 97 awards by dollars obligated in fiscal years 2024 to 2027.
| Award ID | Agency | Type | NAICS | What it buys | Obligated in window | Award value | Starts | Ends | Place of performance | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| 140P2026F0130 | Department of the Interior | Delivery Order | 541310 | GRCA 352837 - NORTH RIM DESIGN SERVICES, AT GRAND CANYON NATIONAL PARK, ARIZONA; ARCHITECTURAL AND ENGINEERING (A-E) SERVICES PLANNING SERVI | $2,881,341 | $2,881,341 | May 12, 2026 | September 30, 2027 | Denver, CO | usaspending.gov |
| 140P2024F0233 | Department of the Interior | Delivery Order | 541310 | GATE 308613 AE DESIGN SERVICES SD-CD ADDRESS DEFERRED MAINTENANCE AT MULTIPLE SITES | $2,091,592 | $2,091,592 | September 9, 2024 | March 11, 2026 | Staten Island, NY | usaspending.gov |
| 140P2025F0317 | Department of the Interior | Delivery Order | 541310 | CUVA 324044 DEMOLISH EXCESS STRUCTURES PDSD AND SUPPLEMENTAL SERVICES | $1,920,512 | $1,920,512 | September 22, 2025 | February 26, 2027 | Cuyahoga Falls, OH | usaspending.gov |
| 140P2026F0158 | Department of the Interior | Delivery Order | 541330 | GRSA 307658 - ENTRY SIGN, FEE COLLECTION, EXPAND THE DUNES PARKING LOT, MEDNO ROAD PARKING AND PARKING AT THE HORSE TRAILER PARKING LOT | $1,667,125 | $1,667,125 | June 22, 2026 | April 28, 2028 | Mosca, CO | usaspending.gov |
| 140P2026F0236 | Department of the Interior | Delivery Order | 541330 | YOSE 352265 AE PD-SD-COMPLIANCE | $1,581,037 | $1,581,037 | September 24, 2026 | April 5, 2031 | Denver, CO | usaspending.gov |
| 140P2024F0330 | Department of the Interior | Delivery Order | 541310 | CHRI 243818, PRESERVE THE STEEPLE BUILDING A-E SERVICES PD & SD & SUPPLEMENTAL SERVICES | $661,473 | $661,473 | August 28, 2024 | August 29, 2025 | Denver, CO | usaspending.gov |
| 140P2024F0098 | Department of the Interior | Delivery Order | 541310 | MALU 293291 -REHAB VC & HQ, FINAL DESIGN | $603,908 | $603,908 | January 29, 2024 | July 1, 2024 | Denver, CO | usaspending.gov |
| 140P2025F0071 | Department of the Interior | Delivery Order | 541310 | FOSU 318708/322870 TITLE III SERVICES REPLACE FORT SUMTER AND FORT MOULTRIE DOCKS, REHABILITATE LIBERTY SQUARE DOCK | $520,829 | $520,829 | January 21, 2025 | December 31, 2026 | Mount Pleasant, SC | usaspending.gov |
| 140P1526C0015 | Department of the Interior | Definitive Contract | 541330 | GLEN CANYON NRA (GLCA)- STABILIZE PARIA RIVERBANKS DESIGN SERVICES FOR PREDESIGN (PD) AND SCHEMATIC DESIGN (SD) DOCUMENTS - PIID# 140P1526R0 | $456,964 | $456,964 | July 28, 2026 | June 1, 2027 | Denver, CO | usaspending.gov |
| 140P2026F0142 | Department of the Interior | Delivery Order | 541330 | STLI 312341 MAIN IMMIGRATION BUILDING T3 | $336,444 | $336,444 | May 19, 2026 | February 17, 2027 | Denver, CO | usaspending.gov |
| 140P2023F0021 | Department of the Interior | Delivery Order | 541310 | STLI-312431, ARCHITECT-ENGINEER CONSTRUCTION SERVICES, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING, STATUE OF LIBERTY NATIONA | $318,100 | $659,744 | April 28, 2023 | July 31, 2025 | Denver, CO | usaspending.gov |
| 140P2025F0195 | Department of the Interior | Delivery Order | 541310 | CALO-226858-LIGHTHOUSE - TITLE III SERVCIES | $317,344 | $317,344 | May 20, 2025 | August 22, 2027 | Denver, CO | usaspending.gov |
| 140P2026F0202 | Department of the Interior | Delivery Order | 541330 | ORPI 240821 TITLE III SERVICES | $310,448 | $310,448 | August 11, 2026 | August 17, 2027 | Carlsbad, NM | usaspending.gov |
| 140P2024F0100 | Department of the Interior | Delivery Order | 541310 | ZION 317454 TITLE III, S. CAMPGROUND BU | $305,206 | $305,206 | January 30, 2024 | September 30, 2026 | Springdale, UT | usaspending.gov |
| 140P2025F0116 | Department of the Interior | Delivery Order | 541310 | GATE 308613 A-E DESIGN SERVICES CONSTRUCTION DOCUMENTS FOR STRUCTURAL STABILIZATION REPAIR B210 STATEN ISLAND, NY | $301,859 | $301,859 | April 10, 2025 | November 15, 2025 | Staten Island, NY | usaspending.gov |
| 140P1324F0136 | Department of the Interior | Delivery Order | 541330 | WABA-A&E DESIGN ON MAINTENANCE BLDG | $297,122 | $297,122 | August 1, 2024 | February 25, 2025 | Cheyenne, OK | usaspending.gov |
| 140P6026F0095 | Department of the Interior | Delivery Order | 541330 | ZION GREENHOUSE AE DESIGN SERVICES | $295,958 | $295,958 | September 18, 2026 | March 5, 2027 | Denver, CO | usaspending.gov |
| 140P2025F0294 | Department of the Interior | Delivery Order | 541310 | MALU 293291 - AE TITLE III SERVICES DURING CONSTRUCTION PHASE TO REHABILITATE THE MARTIN LUTHER KING JR. VISITOR CENTER AND HEADQUARTERS BUI | $275,239 | $275,239 | September 24, 2025 | February 28, 2027 | Atlanta, GA | usaspending.gov |
| 140P2024F0468 | Department of the Interior | Delivery Order | 541310 | CUVA 324044 N200 TO-2 ENVIRONMENTAL SURV | $264,747 | $264,747 | September 26, 2024 | June 30, 2025 | Denver, CO | usaspending.gov |
| 140P1424F0089 | Department of the Interior | Delivery Order | 541330 | GRAND TETON NATIONAL PARK (GRTE) - MORMON ROW CULTURAL LANDSCAPE PLAN DESIGN | $258,750 | $258,750 | June 11, 2024 | September 11, 2025 | Denver, CO | usaspending.gov |
| 140P2023F0291 | Department of the Interior | Delivery Order | 541310 | LARO 258755 REPLACE DILAPIDATED DOCKS AND FUEL SYSTEM, AND REHABILITATE PARKING AREAS AT SEVEN BAYS MARINA. | $216,057 | $1,032,575 | August 17, 2023 | August 1, 2025 | Coulee Dam, WA | usaspending.gov |
| 140P2024F0208 | Department of the Interior | Delivery Order | 541310 | NAMA 340086 REPAIR MALL SINK HOLES, NATIONAL MALL AND MEMORIAL PARKS, WASHINGTON D.C. NATIONWIDE LARGE ARCHITECTURAL & ENGINEERING (AE) SERV | $205,154 | $205,154 | August 19, 2024 | July 22, 2025 | Denver, CO | usaspending.gov |
| 140P2024F0134 | Department of the Interior | Delivery Order | 541310 | ZION 317454 S. CAMPGROUND: TITLE III SRV | $197,608 | $197,608 | March 13, 2024 | September 30, 2026 | Springdale, UT | usaspending.gov |
| 140P2024F0240 | Department of the Interior | Delivery Order | 541310 | LARO-258755-FEE-AE-TO-VM3 | $190,656 | $190,656 | June 13, 2024 | October 1, 2024 | Denver, CO | usaspending.gov |
| 140P1425F0067 | Department of the Interior | Delivery Order | 541310 | LITTLE BIGHORN BATTLEFIELD NATIONAL MONUMENT (LIBI) DESIGN SERVICES FOR CUSTER NATIONAL CEMETERY ARPA PERMITTING AND REMOTE SENSING SURVEY | $179,823 | $179,823 | July 10, 2025 | May 25, 2026 | Denver, CO | usaspending.gov |
| 140P2024F0303 | Department of the Interior | Delivery Order | 541330 | ROMO 316223 TITLE III SERVICES | $176,073 | $176,073 | July 25, 2024 | September 15, 2026 | Denver, CO | usaspending.gov |
| 140P2025F0288 | Department of the Interior | Delivery Order | 541310 | PAGR 335422 REHABILITATION OF UPPER RACE | $170,290 | $170,290 | August 15, 2025 | August 3, 2026 | Denver, CO | usaspending.gov |
| 1240LT24F0008 | Department of Agriculture | Delivery Order | 541330 | CON GAOA PPK MONUMENT FIRE CENTER (MFC) WATER TREATMENT SYSTEM EVALUATION. APPLICABLE CONTRACT: DOI A-E MATOC 140F082D0223 (DHM DESIGN). TEC | $164,116 | $164,116 | March 18, 2024 | October 31, 2026 | Monte Vista, CO | usaspending.gov |
| 140P2024F0335 | Department of the Interior | Delivery Order | 541310 | NAMA 291052 - AE SERVICES FOR CONSTRUCTION DOCUMENTS\LINCOLN REFLECTING POOL | $157,591 | $157,591 | August 13, 2024 | February 24, 2025 | Denver, CO | usaspending.gov |
| 140P2025F0283 | Department of the Interior | Delivery Order | 541310 | GATE 345738 - REHABILITATE HISTORIC SITE LIGHTING AND PROVIDE ACCESSIBLE PARKING IN FT. HANCOCK | $149,878 | $149,878 | August 11, 2025 | September 30, 2026 | Staten Island, NY | usaspending.gov |
| 140P2024F0213 | Department of the Interior | Delivery Order | 541310 | CHRI 243818-PRESERVE THE STEEPLE BUILDING & GUINEA CO WAREHOUSE | $147,806 | $147,806 | May 22, 2024 | June 6, 2025 | Denver, CO | usaspending.gov |
| 140P4224F0035 | Department of the Interior | Delivery Order | 541310 | FRSP DESIGN GEOTHERMAL SYSTEM FOR SJDS | $143,789 | $143,789 | July 18, 2024 | April 30, 2025 | Fredericksburg, VA | usaspending.gov |
| 140P2025F0300 | Department of the Interior | Delivery Order | 541310 | FOSU 318708 - FORT SUMTER REDESIGN | $141,811 | $141,811 | September 5, 2025 | March 31, 2026 | Sullivans Island, SC | usaspending.gov |
| 140P4224F0065 | Department of the Interior | Delivery Order | 541310 | SHEN: A/E SERVICES FOR PINNACLES PICNIC GROUND REHAB | $130,839 | $130,839 | September 3, 2024 | November 14, 2025 | Luray, VA | usaspending.gov |
| 140P2025F0293 | Department of the Interior | Delivery Order | 541310 | NAMA 291052 REFLECTING POOL AE STORMWATER | $125,064 | $125,064 | September 3, 2025 | June 9, 2026 | Washington, DC | usaspending.gov |
| 140P4224F0064 | Department of the Interior | Delivery Order | 541310 | SHEN: A/E SERVICES FOR BIG MEADOWS PICNIC GROUND REHAB | $119,558 | $119,558 | September 3, 2024 | November 14, 2025 | Luray, VA | usaspending.gov |
| 140P1224F0087 | Department of the Interior | Delivery Order | 541330 | GRSA REHAB PINION FLATS CAMPGROUND DESIGN AND CDS | $111,466 | $111,466 | September 10, 2024 | October 3, 2025 | Mosca, CO | usaspending.gov |
| 140P5224F0013 | Department of the Interior | Delivery Order | 541310 | ARCHITECT AND ENGINEERING SERVICES TO DEVELOP CULTURAL LANDSCAPE REPORTS PART 1 AND 2 FOR THE NEW BATTLEFIELD UNITS AT VICKSBURG NATIONAL MI | $79,095 | $79,095 | June 4, 2024 | June 3, 2025 | Vicksburg, MS | usaspending.gov |
| 140P2024F0054 | Department of the Interior | Delivery Order | 541310 | NAMA 291052 AE DESIGN BUILD SERVICES TO REHABILITATE THE LINCOLN REFLECTING POOL | $74,841 | $74,841 | November 29, 2023 | June 30, 2024 | Denver, CO | usaspending.gov |
| 140P1324F0101 | Department of the Interior | Delivery Order | 541330 | ELMA TITLE III SERVICES FOR AE DURING CO | $69,254 | $69,254 | September 9, 2024 | December 11, 2026 | Grants, NM | usaspending.gov |
| 140P4224F0002 | Department of the Interior | Delivery Order | 541310 | COLONIAL NATIONAL HISTORICAL PARK PMIS 307525 REHABILITATE YORKTOWN VICTORY MONUMENT AE SERVICES FOR DESIGN DEVELOPMENT (DD) ALTERNATIVES. | $66,880 | $66,880 | November 29, 2023 | November 4, 2024 | Yorktown, VA | usaspending.gov |
| 140P5226P0057 | Department of the Interior | Purchase Order | 541320 | COMPLETION OF EXISTING LANDSCAPE INV | $66,808 | $66,808 | September 26, 2026 | June 1, 2027 | Mobile, AL | usaspending.gov |
| 140P2025F0141 | Department of the Interior | Delivery Order | 541310 | BOST 325755 - EASTON BLDG SWITCHGEAR REPLACEMENT TITLE III SERVICES | $63,686 | $63,686 | July 28, 2025 | June 6, 2026 | Boston, MA | usaspending.gov |
| 140P1224F0025 | Department of the Interior | Delivery Order | 541330 | AE MECHANICAL ENGINEERING SUPPORT SERVICES ON AN AS NEEDED BASIS TO ASSIST REGIONAL STAFF DURING VARIOUS PHASES (PD, SD, DD, CD & CONSTRUCTI | $35,000 | $35,000 | April 4, 2024 | September 30, 2025 | Denver, CO | usaspending.gov |
| 140P1423F0058 | Department of the Interior | Delivery Order | 541330 | LIBI-CUSTER NATIONAL CEMETERY IRRIGATION | $33,000 | $238,976 | April 17, 2023 | August 29, 2025 | Crow Agency, MT | usaspending.gov |
| 140P1222F0060 | Department of the Interior | Delivery Order | 541330 | BLCA AMPHITHEATER REHAB/RECON FOR ACCESSIBILITY - AE SERVICES FOR SCHEMATIC DESIGN SERVICES AND CONSTRUCTION DOCUMENTS FOR BLACK CANYON OF T | $28,354 | $112,614 | September 12, 2022 | August 13, 2024 | Gunnison, CO | usaspending.gov |
| 140P1226F0033 | Department of the Interior | Delivery Order | 541330 | IMRO MECH ENG SERVICES FY26 AAP#8503 | $25,000 | $25,000 | September 23, 2026 | September 24, 2027 | Denver, CO | usaspending.gov |
| 140P1226F0034 | Department of the Interior | Delivery Order | 541330 | IMRO ELEC ENG SERVICES FY26 AAP#8505 | $25,000 | $25,000 | September 23, 2026 | September 24, 2027 | Denver, CO | usaspending.gov |
| 140P8523F0109 | Department of the Interior | Delivery Order | 541310 | TITLE I PRELIMINARY AND SCHEMATIC DESIGN SERVICES, REPLACE DILAPIDATED MOORAGE DOCK SYSTEM AT KETTLE FALLS MARINA, LAKE ROOSEVELT NATIONAL R | $20,491 | $186,658 | August 21, 2023 | February 4, 2025 | Coulee Dam, WA | usaspending.gov |
| 140P4322F0023 | Department of the Interior | Delivery Order | 541330 | SAMA AE SERVICES CENTRAL WHARF DOCK | $18,696 | $95,493 | September 21, 2022 | April 12, 2024 | Salem, MA | usaspending.gov |
Also on SpecStream
- All recipients under NAICS 541310 Architectural Services
- All recipients under NAICS 541330 Engineering Services
- All recipients under NAICS 541320 Landscape Architectural Services
- Open opportunities under NAICS 541310
- Open opportunities under NAICS 541330
Updated October 6, 2026. Read from USAspending.gov. Public U.S. federal spending data (U.S. Department of the Treasury). Obligations are the contract actions dated in fiscal years 2024 to 2027 of the USAspending.gov award archive of 2026-10-06; a contract's total value is its current value as USAspending reports it, including earlier years. Recipients are matched on their SAM.gov UEI, never on the name, and are shown as the government prints them. Sole proprietorships and opted-out entities count in the totals and are not named. Free to reuse with credit to SpecStream under CC BY 4.0. Spot a wrong value? Write to [email protected] with the link to this page.